In May 2008 the Südwestrundfunk (“South-West Brodcasting”) began with the construction of its new 86.5 m euro building next to the SWR Funkhaus in eastern Stuttgart. The new building brings together several departments previously scattered across the Stuttgart area. The building houses television and radio studios and offices on a floor area of some 22,000 square metres. The new building offers one of the most “state-of-the-art” media production facilities in Germany.

The SWR and its architects also chose the facade cladding based on functionality and innovation. A curtain-type, rear-ventilated facade system consisting of fibreC facade panels was not only in compliance with the Energy Saving Regulation, but also met the requirements of the city of Stuttgart which had further reduced target values by 20 percent. "All our decisions are based on feasibility studies”, Vocke pointed out. For the construction of the SWR building we only chose building materials which would pay off in the long term.

The fibreC facade cladding is designed as curtain-type, rear-ventilated facade which shapes the character of the building envelope. This system ensures a well-balanced indoor climate, protects the building against driving rain and condensate and provides noise insulation. Apart from constructional advantages, a curtain-type, rear-ventilated facade also offers economic benefits: controllable manufacturing costs, installation independent of weather conditions, durability and zero maintenance.

Facts
Project.  Construction of new SWR building
Size 22,000 m2 floor space

Facade
Surface: 5,500 m2 fibreC 13mm
Colours: silver grey, anthracite, ivory & special colours
Surface finishes: Ferro light & Ferro
Principal: Südwestrundfunk
Planner: Struhk Architekten Planungsgesellschaft mbH (general planner and architect)
Beginning of construction: 2008
Completion: Summer 2011